  • Platforms extension work at Sealdah station is on keeping suburban train movement normal. See, how three trains enter and leave sealdah station with in a very short period of time .
    This platform extension work was long pending. finally this work has been taken up.
    Platform number 1 to 4 are being increased in length, so that 12 coach EMU can be accomodated. Presently these platforms are around of 210 metres in length. Which will be increased by another 60 metres. Out of that 10 metres extension has been already done on the buffer end. Rest of 50 -60 metres are being increased on the rear end.

ความคิดเห็น • 5

  • @minatimurmu9798
    @minatimurmu9798 4 หลายเดือนก่อน +1

    How many platforms are getting extended in Sealdah?
    And what will be their total length after extension?

    • @Rail_road_and_more
      @Rail_road_and_more  4 หลายเดือนก่อน

      Platform number 1 to 4 is extended. Length is expected to be increased from 210 metres to 270 metres.

    • @minatimurmu9798
      @minatimurmu9798 4 หลายเดือนก่อน

      @@Rail_road_and_more What about the others

    • @Rail_road_and_more
      @Rail_road_and_more  4 หลายเดือนก่อน

      @@minatimurmu9798 other platforms can accommodate 12 coach rakes ....