@@vibhanshu1 temp. rise rate of furnace metal should be 1 degree/ min. upto 100 ° C & After that 1.5 to 2 ° C / min and the Pr. raising rate should not be more than 0.12 mpa/min
@@vibhanshu1 In case of cold lit up ,mill may be taken into service after synchronisation of unit but in hot lit up,mill is taken into service just after lit up to maintain and increase the MS temp
@@rahulsirclasses1987 800 mw me jo basic difference rahta hai uspe video banaiye ga sir our yadi coal feeder trip kar jaye to kitne time tak oil gun ka use kar sakte hai.
Much informative sir.
Thanks
great knowledge sharing sir, very informative
Thanks
Thank you very much sir
Thanks
बहुत आच्छा गुरु जी प्रणाम 🙏🙏
Dhanyawad
Excellent
Thanks
Very informative video sir
Thanks
Thanks
Dear sir
Please cover topic major emergency what action to be taken during operation 🙏🙏🙏🙏
Ok
Hamare yha 250mw m ........sost ka lvl high hone k baad oil mot m jaata hai .....aur sop suction leta hai vacuum tank m .....
Some arrangements in 250 MW plant are different from that of 500 MW
One lecture on H2 dryer sir...
Yes
Will make video
Sr boiler material pr bhi vedio banaye kaha kaun sa tube material hai plj bataye
Ok
Sir please explain about 24v tg and sg charger also abou48V charger and about ups
@@abhi_06kumar ok
Sir, please make a video on 3 element controller logic on boler Drum
Ok
Rate of rise of metal temperature kitna rakhna hai cold , warm and hot light up mein. Mill should be taken before synchronisation or not and how many
@@vibhanshu1 temp. rise rate of furnace metal should be 1 degree/ min. upto 100 ° C & After that 1.5 to 2 ° C
/ min and the Pr. raising rate should not be more than 0.12 mpa/min
@@vibhanshu1 In case of cold lit up ,mill may be taken into service after synchronisation of unit but in hot lit up,mill is taken into service just after lit up to maintain and increase the MS temp
Sir Is acw pump having recirculation line?
Yes
Vaccum pump PHE me ACW cooling water hi use kyo karte..
In some plant use TGECW water also
TG DMCW
Kitne capacity ke boiler ka light up procedure hai ya fir sab ka same hota hai
Basic procedure same rahta h .Thora sa difference rahta h
500 MW
@@rahulsirclasses1987 800 mw me jo basic difference rahta hai uspe video banaiye ga sir our yadi coal feeder trip kar jaye to kitne time tak oil gun ka use kar sakte hai.
Ok@@veerkumarshah5622