The question is just confusing because of the wording. But if you read carefully, you will see that 7.5 is the total from the chart. Meaning 3.5 Arch, 2.0 MEP, 0.5% S, and 1.5 Civil. But the question is simply what's in for the architect, so 3.5% of the budget and from that just 15% because they are talking about SD phase only.
Super helpful video. Thank you!
I think question 4 is the 3.5% of the 7.5% (total design budget) which is not an answer on the options.
The question is just confusing because of the wording. But if you read carefully, you will see that 7.5 is the total from the chart. Meaning 3.5 Arch, 2.0 MEP, 0.5% S, and 1.5 Civil. But the question is simply what's in for the architect, so 3.5% of the budget and from that just 15% because they are talking about SD phase only.
@@agrelostudio don’t know how I read it at that time but it is correct. 32, 550 bcs is only SD phase and even the total is there. 217,000 😅. Thanks