TWO-WAY SLAB REBAR ARRANGEMENT & INSTALLATION SEQUENCE | How to install rebars on suspended slab
ฝัง
- เผยแพร่เมื่อ 3 ม.ค. 2025
- Suspended slab/Two-way slab/One-way slab
Today's video answers the questions I get asked most frequently:
How do you read or interpret slab reinforcement placement? (Paano magbasa ng plano ng slab ng bahay)
Suspended slab rebar arrangement procedure
Visit and follow our facebook page for more educational content: / mannelearningacademy
All photos/music are reserved to the owner/s or copyright holders. If you are the owner or copyright holder, please contact me to claim your ownership or removal of such to this video.
Other related contents:
AutoCADD at SURVEYING Gamit ang Total Station? Kailangan Alam Mo Ito
• AutoCADD at SURVEYING ...
Horizontal Curve Layout with Total Station (Part 2)
• Horizontal Curve Layou...
Papaano ba mag-layout ng Horizontal Curve Basic Tutorial (Part 1)
• Papaano ba mag-layout ...
Road Construction Series 4: Surveying Part 4 (Profile Leveling)
• Papaano nga ba ang Pro...
Benchmark Leveling | Papaano maglagay ng elevation sa bagong puntos o Benchmark?
• Paano maglagay ng elev...
ROAD CONSTRUCTION TIPS and TRICKS (Survey Basics 101)
• Construction Workers N...
ROAD CONSTRUCTION TIPS and TRICKS (Orientation / THE BASICS)
• ROAD CONSTRUCTION TIPS...
Beam Splicing Details
• BEAM REBAR SPLICING DE...
Ano ba ang pundasyon ng isang SAFE na bahay? • Alamin kung BAKIT MAHA...
Self-check for earthquake safety of concrete hollow block (CHB) houses in the Philippines:
• Self-check for earthqu...
Construction Learning Series #5: Matibay ba ang bahay mo? Beam Construction (Part 1: Introduction) • Construction Learning ...
Construction Learning Series #6: Tips para sa matibay na bahay / Safe ba tayo? (Part 2 Beam Details) • Construction Learning ...
Construction Learning Series #7: Lindol nung Xmas Safe ka ba? Alamin ang dapat sa matibay na bahay • Construction Learning ...
// Credits
Respective plans used in this presentation were solely copyrighted to its individual owner.
//Music credit:
Ikson - New Day
Music by: / ikson
MARCSAM Construction
Manne Learning Academy
Keep safe everyone!
God bless us all!
This gives everyone the basic idea of how the 2-way slab works.
sir sa kaalaman at experienced ay unang ilatag ang biga na pahaba (long side of the building) two sides tapos ipatong ang 2 sides ng maiksing biga. NGAYON dun tayo (1) mag sisimulang mag slab sa main distribution bars short distance bars sa ilalim ng top beam rebars (long span). (2) latag ay long distance bars sa ilalim nmn ng top beam bar (short span) (3) latag ay long distance PA RIN (sa ibabaw naman ng the very top beam bars at (4) last latag ay yun No. (1) na short distance bars at the very top of long beam bars. yun cranks topic ay plano na ang sundan. purely kasador lng poh hmmm nakuwa kaya ang paliwanag ko. folks cheers
👍
Thanks po dito! Isa po akong engr na kakapasa lang sa board exam. Buti nandyan ka po thank you. Bat po pala nag lalagay tayo ng concrete spacing baka to bakal?
Sir salamat po sa panibagong video mo, keep safe po.
Salamat boss
Galing nyo pomag paliwanag para akong nag tesda pwede po mkahingi ng nc 2 namamayaw ako nlng ako kc mahina n ako magtrbaho
Magkano po nc2
Very informative sir....Tanong ko lng po sir ano po sukat ng bent bars gaano kahaba yang nka 45 degrees...Salamat sa pagsagot sir 😊
Nice lods
Hi Sir, no against po. would like to clarify lang di po ba dapat first to place yun Bottom Bar (Main bar) and Crank Bars along SP which is perpendicular to LS?
Hi Sir. Thank you for the input. Yes po. Nagkakalituhan lang po sa part na ito. Tama po na perpendicular sa long span ang placement ng bottom bars. Kaya kung makikita ninyo sa presentation natin, makikita ang long span. Meaning, inuna natin yung mga bakal na nasa short span (mas maiikli) perpendicular sa direction ng long span (mas mahaba). Saka naman ipapatong yung mahahabang mga bakal (along sa direction ng short span) o tatakbo sa kahabaan ng short span.
SS over LS
Good day engineer eto n rin po ba tinatawag na C type?
Engr, Bakit dinideretso na nila iyong bakal wala nang bend yung mga iba para sa two way katulad ng isang pic dito 1:07 ?
Idol ilang layer ng bakal ba dapat sa slab
! layer po usually pero may instances na 2 layers depende sa loading o bigat na dadalhin niya. For economy, 1 layer ay okay na basta sundan lang ang tamang requirement o detalye. ng plano.
Sir papano poba mag sukat sa pag bali ng el over 4 slmt?
Sukatin niyo po ang clear span o yung loob-loob na distance tapos hatiin niyo po sa apat. Yun po ang L over 4. 🙏
Applicable parin po b ung 9mm reinforcement 1way for 2nd flooring n slab? Slamat po s ssgot
Me gumagamit naman po nyan pero syempre kelangan pa din po computation para safe
ask ko lang po required po ang bend bars?
Kung nasa design po, yes po required. Pero kapag ang ginawa ni designer ay may top and bottom bars na deretso, no need na ang bend bars.
@@ManneLearningAcademy thanks po junior architect po kasi salamat sa pagsagot
Hi eng. you naka bend po ba sa L4 na 35% or 45%, halimbawa 4M ung clear span. sa 1meter naka bend for both sides po? salamat po.
Kung continuous po ang beam, both sides po siya. Yung 1m sa Isang side at sa another 1m sa kabilang side. Kung discontinuous, Yung sa 1m na lang po.
Thank you!
Good day po sir, tanong ko lng po. pwd po ba kahit saan mag dugtong ng bakal sa slab?
Dina po ba yan itatali ng gi wire?
kailangan po talian ng tie wire para po nasa tamang lugar ang mga bakal
Sir ask lang ano po ang dapat gawin balak ko kasi sana mag pagawa ng 2nd floor...kaso yong budget kolang pwdi pobang i abang konalang sa beam or buhusan ng buo ang beam at ipatung nalang ang slab or buhusan ng higit sa kalahati? Tnx po
Ideally, dapat po magkasunod na buhusan ang beam at slab. Una muna ang beam up to bottom level ng slab then after makumpleto lahat ng beam paikot, kasunod na ang slab. But sa actual na construction, may mga gumagawa na bubuhusan muna ang beam up to bottom slab level then after sometime saka naman ang slab. Dini discourage po natin ang ganitong method. Na discuss na po natin kung bakit. Pero kung di maiiwasan tulad nga ng budget constraint, better na ikonsulta natin sa structural designer natin para safe tayo. May option kasi na maglagay ng shear bars sa ibabaw ng mga beams kung sakali na gagawa tayo ng ganitong istilo. Alamin natin sa ating designer ang tamang laki at spacing ng shear bars kung papayagan niya. Salamat po.
Salamat po dito sir,kahit steeldeck po ba gagamitin kilangan parin masunod Yung ganyang latag ng bakal,Yung sa akin po kasi ganyan ang pagkalatag ng bakal kaso steel deck po gigabit baka sabihin over kill na po,karamihan kasi nakikita ko pagdecking di ganyan gamit po Nila,Sana mapansin nyo po ito
Kung gagamit po kayo ng steel deck mas konti po ang bakal na magagamit ninyo. May suggested design po ang supplier. Better ask po ang supplier then pa approve niyo po sa engineer ninyo para sigurado.
Along = Parallel
About = Perpendicular
Ang alm q jn pg bend up design. Ung bend up bars must be lay only in the mid. S loob ng L/4 ng slab
Tama po. Pwede along the whole span kung one way sia.
Ilan po ang spacing ng mga bars nakalatag sa slab min to max?
Ang dami po yatang layer ng bakal nyo lulutang po yan sa buhos
Paano po maglagay ng biga at poste kapag naiipit ka ng dalawang bahay magkabila at iisa ang mga ding ding nyo? Plano ko po magpa-second floor, residential po ito.
May dating bahay na po. Sa isang hilera tatlo po kaming bahay. Nasa gitna po yung sa akin. Plano ko po magpasecond floor.
Thank you in advance.
Ipagawa niyo po ang plano sa arkitekto o civil engineer. sila po gagawa ng paraan para mabuo ang bahay ninyo ng naaayon sa building code requirements.
Konsulta po kayo sa Arkitekto alam nila yaan naaayon sa Building Code...
bakit po naka bend po ang nasa loob ng L/4 hindi po topp bar at bott.bar lang
Kng 2 way ito parang sobra sa bkal.
May cut bars meron pang top bars,
Malayo sa design ni Sy2 na bothways bb then both ways xtra sa mid at sa top bars ay cut bars lng sa l/4. At lumang design na yang bend up, maxado hussle,
For presentation purposes lamang po ito. Kaya po kailangan natin i check requirement ng ating mga plano. Depende pa rin po sa designer at sa requirement ng design.
Wala concrete cover Ka Aya pumutok
Pg s 10 mm ang kapal Ng slab Wala n ung concrete covering nya
Medyo bitin yng content mo sana explain mo din difference ng 2way s 1way slab pr maintindihan ng followers or subscriber mo ano ang essence ng bent bars.
May separate discussion po tayo sa 1 way slab. Paki check na lang po ibang video natin. salamat po
Gaanopo oanopo Ang saktong skat ng 120x3.0
Common sense p rin yan..kya nga my one way at two way..ttanungin mo qng anu difftence syempre latag p rin mg bakal..rebar slab works nga usapan..mahina lng ulo mo brod..wag mo sisihin si Engr.kya pla name mo rocco rocco..roco roco k pla!
Parang Mali po yata, mag kakaiba ang one way, two way at both way slab,?
Anung both way skab??kkaiba n yn ah!
@@MadaraUchiha-vv6qfang one way slab bottom bars at extra top bars paikot, gamit s mga high rise building, ang two way slab bottom bars at top bars, same amount Ng bakal gamit s mga fly over, mga Tulay, ang both way slab ay ang video, bottom bars magiging top bars, Yan ang latag s Philippine Arena, paki Tama Kung Mali ang experience q,
@@ronalddelacruz605 dq mkuha punto nyo..anung ang top bars mgging bottom bars? Top bars nga paanung mgging bottom bars gaya ng latag sa phil.arena?? My uri pla ng latag ng one way at two way n ginagamit sa hi rise at sky way?? Ee nka depende nmn sa structural design yan qng one way or two way base sa plano..
Bakit ang bagal nagbabasa lang yata ito 😀
😀