Navisworks Quantification for takeoffs

แชร์
ฝัง
  • เผยแพร่เมื่อ 9 ก.พ. 2025
  • Navisworks Quantification workbook for estimating and take-offs

ความคิดเห็น • 19

  • @anuragpatil6973
    @anuragpatil6973 3 ปีที่แล้ว +2

    great video sir. very helpful :)

    • @unidesigndc
      @unidesigndc  3 ปีที่แล้ว +1

      Your Welcome Anurag

  • @ghaithtaher9907
    @ghaithtaher9907 2 ปีที่แล้ว +1

    Thank you very much I have a problem when i click right click the “ take off “ bar doesn’t appear, anyone know the solution?

    • @unidesigndc
      @unidesigndc  2 ปีที่แล้ว +2

      Hi not sure why that is happening. Are you using Navisworks manage?

    • @ghaithtaher9907
      @ghaithtaher9907 2 ปีที่แล้ว +1

      Thank you very much for the answer, now i found it but i faced another problem, it will be really appreciated if you can help me in it
      I tried three models, the three of them they gave fore me for each element “length, volume , width … etc “ = zero meter
      No numbers no length just zero

    • @unidesigndc
      @unidesigndc  2 ปีที่แล้ว +1

      @@ghaithtaher9907 Hi not sure why you are only getting zero. Check all your setting. I would have a look but I don't have Navisworks at the moment but I will soon.
      Robert

    • @ghaithtaher9907
      @ghaithtaher9907 2 ปีที่แล้ว +1

      Oh ok, thank you, i hope that i can find something in the settings

    • @ghaithtaher9907
      @ghaithtaher9907 2 ปีที่แล้ว +1

      The main file is IFC file, this maybe the problem or not?

  • @fatihcengiz16
    @fatihcengiz16 2 ปีที่แล้ว +1

    I couldn't find the way to takeoff pipes, cable trays, conduits lenghts according to sizes such as 4", 500x100, Ø50..., it is giving bulk lenghts, not separated diameter sizes

    • @unidesigndc
      @unidesigndc  2 ปีที่แล้ว +1

      Hi Fatih, I had the same problem too. What I have done for sizes of pipe size and fitting in the past was to do them in Revit, because I haven't as well figure that one out. Very sorry I can't help but I will investigate, we did a data center tons of pipes conduit etc. we had to quantify pipes and fittings in Revit.

    • @fatihcengiz16
      @fatihcengiz16 2 ปีที่แล้ว +1

      @@unidesigndc Thanks for your quick response, I'm working in subcon scope is not included design, our contracter dont release us rvt files. they are sending nwd , dwg , pdf files. thats why I need to find easy way to takeoff quantity. otherwise it is taking so long time

    • @unidesigndc
      @unidesigndc  2 ปีที่แล้ว +1

      @@fatihcengiz16 Wow the contractor has to release the revit model, because that's all you can do, how do they expect for you to do coordination. I would do what we call is a contingency stating we could not do an accurate take-off because we don't have access to the Revit model....wow you are going through what I go through on my job its hard working for people that don't understand what we do