Hi Sir- incase if I have more than 3 scrips and each script has 10 transactions then we should consider total transactions are 30 right.. And also why we consider 6 users in your formula, what if 9 users or more users takes .. Please explain
According to formula I can achieve my Target with 2.5 users but I want to use some delay for which am increasing user load to 6, we can also user 9 user's but think and pacing should give more..
Hi I am jeetendra Gaherwar I have to buy your complete performance testing with jmeter kindly suggest how to I achive & buy your complete performance testing package
Hi I am new to Jmeter and performance testing. I have requirement to achieve 10TPS with 12 transactions for 2 hours. If I don't know the iteration time, how do I calculate VU,Think time, pacing. Can you please help on this.
@@rizwanamd8445 okay here you have 12 transactions you have to achieve 10 tps for 2 hours = 10*7200(2 hrs in seconds) --72k transactions should be executed in 2 hour's that's the case Assume your 1 iteration time is - 25 second You need to make total of - 72000/12 = 6000 iterations If you take 1 users am obviously it takes more than 2 hours Assume you taken 30 vu Assume you have taken 30 users 6000/30= 200 iterations 200 * 25 (1 iteration time) = 5000 seconds Total time is 7200-5000 = 2200 2200/200 = 11 Seconds as pacing you can use Conclusion - with 30 VU and 11 Seconds pacing you can achieve this 10 tps
As it's just 6 users gave 1 sec for each user, you can give as per your requirement,, ramp up is just to see while user's gradually increasing is there any spike in responses or its constant...
Here 175/25 means we need to do total 25 iterations which is nothing but each iteration user should wait for 7 seconds. If it is 175/8 will be around 22 seconds it's huge delay..
Hi Manila, If you give thread group to 1 and ramp up 1 and iterations to 150 For example your script contains 8 transactions then it will be 150 *8 = 1200 transactions will be executed.. Thanks
@@udaykumar-mu5cu Exactly that would be 150 per API with a total of 1200 samples or TPH but my question was, what's the diffrerence to the values you set on the thread group. Cheers!
Thank good Informative Content Again...
Very informative thanks for the video 🎉
Thanks for explaining this so clearly sir.
Can you please explain total extra time you added as a thinktime where you added pacing?
Could you please explain why you are dividing 175 / 25 at 8:34, shouldn't it be 175 / 150 iterations???
Because we are going to do it with 6 users 6 * 25 = 150 , that's why we are dividing it with 25 iterations
Very Helpful video
Nice content thanks
Nice content
Hi Sir- incase if I have more than 3 scrips and each script has 10 transactions then we should consider total transactions are 30 right.. And also why we consider 6 users in your formula, what if 9 users or more users takes .. Please explain
According to formula I can achieve my Target with 2.5 users but I want to use some delay for which am increasing user load to 6, we can also user 9 user's but think and pacing should give more..
We need more content related to think time and pace in more detail
Sure will make a another video for this topic 👍
if the iteration time is 5 sec at one time and 7 or 10 sec another time i.e dynamic then how we will calculate the iteration time
Take average one from 1 user 10 iterations,so that you get accurate value
Hi I am jeetendra Gaherwar I have to buy your complete performance testing with jmeter kindly suggest how to I achive & buy your complete performance testing package
Hi Jeetendra, soon am planning to upload complete JMeter package in detailed way.. thanks..
superb explanation :)
Thanks 😊
Hi I am new to Jmeter and performance testing. I have requirement to achieve 10TPS with 12 transactions for 2 hours. If I don't know the iteration time, how do I calculate VU,Think time, pacing. Can you please help on this.
@@rizwanamd8445 okay here you have 12 transactions you have to achieve 10 tps for 2 hours = 10*7200(2 hrs in seconds) --72k transactions should be executed in 2 hour's that's the case
Assume your 1 iteration time is - 25 second
You need to make total of - 72000/12 = 6000 iterations
If you take 1 users am obviously it takes more than 2 hours
Assume you taken 30 vu
Assume you have taken 30 users
6000/30= 200 iterations
200 * 25 (1 iteration time) = 5000 seconds
Total time is 7200-5000 = 2200
2200/200 = 11 Seconds as pacing you can use
Conclusion - with 30 VU and 11 Seconds pacing you can achieve this 10 tps
Sir in my jmeter whatever website I am testing it is showing 100 percentage error
why rampup time we assumed 6 sec
As it's just 6 users gave 1 sec for each user, you can give as per your requirement,, ramp up is just to see while user's gradually increasing is there any spike in responses or its constant...
super sir
Jmeter course undha sir for career gap
175 / 8 transaction right but not 175/25, bcz we have only 8 transaction in script not 25 transaction. 25 transaction per user complete count ,
Here 175/25 means we need to do total 25 iterations which is nothing but each iteration user should wait for 7 seconds.
If it is 175/8 will be around 22 seconds it's huge delay..
I’m not sure I understand, what’s the difference if you set the
Thread to 1
Ramp up to 1
and Iterations to 150
Cheers 🎉🎉🎉
Hi Manila,
If you give thread group to 1 and ramp up 1 and iterations to 150
For example your script contains 8 transactions then it will be 150 *8 = 1200 transactions will be executed..
Thanks
@@udaykumar-mu5cu Exactly that would be 150 per API with a total of 1200 samples or TPH but my question was, what's the diffrerence to the values you set on the thread group.
Cheers!
If 1200 TPH means.. each transaction 1200 times, but you achieved all together.. Here your TPH 150, not 1200
My requirement is to to achieve 1200 tph all together not individual transaction level..
Yes right
Tph would be transactions per hour, not total, in this case to achieve 1200 txs you need 750 users to achieve 1200 at 1.6s per transaction