High Voltage Diagnostics HVA Series Serial Communications Setup
High Voltage Diagnostics HVA Series Serial Communications Setup
In this video, Bret Hammonds shows you how to connect an HVA series Universal VLF & DC HV Test System unit to a laptop, and navigate the HVD ControlCenter software settings to allow the computer to communicate with the unit.
HVA units may not possesses Bluetooth communication capability (HVA30's, HVA60's and others). You have use the 9-pin serial connector on the side of the test set, but not apparent to reach the connector on the unit. You must remove the black box on the side with the USB port to expose the serial connector. Watch the video for complete instructions.
To rent High Voltage Diagnostics Units, visit Protec Equipment Resources:
protecequip.com/products?q=HV+Diagnostics+HVA&manufact=&category=&subcat=&search-home=
มุมมอง: 109

วีดีโอ

How to Unlock the GE TVRMS2 Digital Test Kit Handle Without Breaking It!
มุมมอง 785 หลายเดือนก่อน
How to Unlock the GE TVRMS2 Digital Test Kit Handle Without Breaking It! Are you having trouble getting the handle to unlock or move to a new position on your GE TVRMS2 Digital Test Kit? This quick video shows you the SECRET of how to unlock the handle without breaking it, and using the handle as a resting stand. The biggest repair to this unit is a broken handle! By simply pulling out (away fr...
Transformer Excitation Current Testing
มุมมอง 2.9K10 หลายเดือนก่อน
Transformer Excitation Current Testing This webinar covers the importance of excitation current testing and explains the physics behind the test. We will cover: - Refresher on Magnetism - Magnetic Induction - Lenz’s Law - The Importance of Excitation Current Measurements - Understanding the physics behind the test - Finding Faults - Tests Performed - Understanding phase patterns - Phase Pattern...
Mastering Transformer Winding Resistance: Insider Tips and Tricks
มุมมอง 2.9K10 หลายเดือนก่อน
Mastering Transformer Winding Resistance: Insider Tips and Tricks Winding resistance measurements in transformers are of fundamental importance for the following purposes: - Calculations of the I2R component of conductor losses. - Calculation of winding temperature at the end of a temperature test cycle. - As a diagnostic tool for assessing possible damage in the field. In addition to the obvio...
Doble TR3190 Transducer: A Comprehensive Overview and Setup Guide
มุมมอง 23111 หลายเดือนก่อน
Doble TR3190 Transducer Overview and Setup Guide The Doble TR3190 transducer can be used either as a linear transducer or rotary transducer. There are a few things we need to know about the configuration of it. Use the Doble TR3190 with circuit breaker motion analyzers to time breakers and verify parameters of the operations of the circuit breaker. The Doble TR3190 Linear and Rotary Transducer ...
Quick Start HV PDTD60 Setup and Operating the HVD Software Suite for Partial Discharge Testing
มุมมอง 1.5K11 หลายเดือนก่อน
We're doing this old-school format! This HV PDTD60 partial discharge demo video serves as both product demonstration as well as a Quick Start guide demonstrating all of the accessories proper connection procedure and how to set up the HVD suite software for doing an automatic capture of partial discharge. Rent the HV PDTD 60-2 here: protecequip.com/products/hv-diagnostics-pdtd60-2-partial-disch...
Understanding High Potential Testing
มุมมอง 1.8Kปีที่แล้ว
Protec Equipment Resources Webinar September 2023: Understanding High Potential Testing In electrical testing and maintenance, a dielectric withstand test (or pressure test, high potential or hipot test) is an electrical test performed on a component or product to determine the effectiveness or strength of its insulation. The test may be between mutually insulated sections of a part, or energiz...
Understanding Insulation Resistance Testing
มุมมอง 2.7Kปีที่แล้ว
Understanding Insulation Resistance Testing, September 2023 Webinar by Tom Sandri of Protec Equipment Resources. In this webinar, we will review insulation and its properties along with basic causes of insulation degradation. We will learn how insulation resistance is measured and how an insulation resistance test set (megohmmeter or hipot) operates. Proper use of an insulation test set along w...
Exploring Power Factor / Dissipation Factor Testing
มุมมอง 3.6Kปีที่แล้ว
In this video, join Tom Sandri as he Explores Power Factor / Dissipation Factor Testing. Most failures of electrical equipment are the result of a breakdown in the insulation system. Power factor/dissipation Factor testing is an effective way to detect defective electrical equipment insulation. Power factor/dissipation factor is the ratio of the capacitive or ‘charging’ current (measured in vol...
Ground Fault Protection Detection and Locating Ground Faults
มุมมอง 4Kปีที่แล้ว
Ground Fault Protection Detection and Locating Ground Faults This webinar will focus on locating ground faults in ungrounded DC battery systems. Various standards require action when the impedance between any battery polarity and ground falls below a specified limit. In the case of nuclear-fueled plants, the Nuclear Regulatory Commission (NRC) requires audits and appropriate action when this im...
Introduction to Potential and Current Transformers
มุมมอง 1.8Kปีที่แล้ว
Introduction to Potential and Current Transformers Current transformers and potential transformers are commonly used devices found in metering and protective relay applications for the electrical power industry. The purpose of these devices is to scale large primary currents and voltages to a smaller, easy to measure, secondary current or voltage. The devices also isolate the measuring and reco...
NERC Standards 2010-2012 Update: Understanding Compliance and Testing Requirements for Asset Owners
มุมมอง 297ปีที่แล้ว
NERC Standards 2010-2012 Update: Understanding Compliance and Testing Requirements for Asset Owners. Disclaimer: This is a Tom Sandri classic video from 2012. The material in this video is dated and updates to the standard may be available, but this video will give you a great overview of NERC. If you want to see Tom do a current update, put a comment below! 0:00 Reliability Challenges - Power ...
Megger Bite 2P Battery Impedance Test Set Overview and Demonstration
มุมมอง 681ปีที่แล้ว
In this video, Tom Sandri gives a Megger Bite 2P Battery Impedance Test Set overview and demonstration. This is a Tom Sandri classic video from 2012. The material in this video may be dated and newer models available. And yes, we know the video is shaky and sucks, but the information is good! Maybe we'll have Tom reshoot this one soon :) To rent the Megger BITE2P Battery Impedance Test Set (US ...
Megger PFL22M1500 Power Cable Fault Location System Overview
มุมมอง 557ปีที่แล้ว
Megger PFL22M1500 Power Cable Fault Location System Overview
Doble DTA Pro vs Doble DTA Basic Software for the Doble M4000 / M4100 - Which One Do I Need?
มุมมอง 827ปีที่แล้ว
Doble DTA Pro vs Doble DTA Basic Software for the Doble M4000 / M4100 - Which One Do I Need?
A Testing Strategy For Fiber Optic Cables
มุมมอง 668ปีที่แล้ว
A Testing Strategy For Fiber Optic Cables
Time Domain Reflectometry (TDR): Technology Review and Applications
มุมมอง 4.1Kปีที่แล้ว
Time Domain Reflectometry (TDR): Technology Review and Applications
Tom Sandri's Ultimate 5-Hour Cable Fault Locating Course - Webinar Replay
มุมมอง 2.3Kปีที่แล้ว
Tom Sandri's Ultimate 5-Hour Cable Fault Locating Course - Webinar Replay
How to Pair a Bluetooth Connection with HV Diagnostics VLF Unit HVA28TD #shorts
มุมมอง 365ปีที่แล้ว
How to Pair a Bluetooth Connection with HV Diagnostics VLF Unit HVA28TD #shorts
HV Diagnostics HVA28TD Communications and Bluetooth Pairing
มุมมอง 880ปีที่แล้ว
HV Diagnostics HVA28TD Communications and Bluetooth Pairing
Acceptance and Maintenance Testing of Medium Voltage Electric Power Cables, Part 1
มุมมอง 520ปีที่แล้ว
Acceptance and Maintenance Testing of Medium Voltage Electric Power Cables, Part 1
How to Program Trip Unit Test Sequences into the ABB SACE PR010/T Secondary Injection Test Set
มุมมอง 1.4Kปีที่แล้ว
How to Program Trip Unit Test Sequences into the ABB SACE PR010/T Secondary Injection Test Set
Setting Up and Communicating With the Fluke 1750 Power Recorder & Analyzer
มุมมอง 1.8Kปีที่แล้ว
Setting Up and Communicating With the Fluke 1750 Power Recorder & Analyzer
Ground Resistivity & Ground Resistance
มุมมอง 1.3Kปีที่แล้ว
Ground Resistivity & Ground Resistance
How to Fix Doble M4000 M4100 Hand Interlock Error Message
มุมมอง 611ปีที่แล้ว
How to Fix Doble M4000 M4100 Hand Interlock Error Message
Investigation of Cable Failures at Wind Farms
มุมมอง 379ปีที่แล้ว
Investigation of Cable Failures at Wind Farms
Benefits of Battery Testing - Ohmic Trending (Protec December 2022 Webinar)
มุมมอง 496ปีที่แล้ว
Benefits of Battery Testing - Ohmic Trending (Protec December 2022 Webinar)
Importance of Demagnetization of Transformer Cores (Protec November 2022 Webinar)
มุมมอง 747ปีที่แล้ว
Importance of Demagnetization of Transformer Cores (Protec November 2022 Webinar)
Testing for Partial Discharge - Exploring Online Techniques (Protec October 2022 Webinar)
มุมมอง 726ปีที่แล้ว
Testing for Partial Discharge - Exploring Online Techniques (Protec October 2022 Webinar)
Benefits of Battery Testing - How To Perform Capacitance Test (Protec August 2022 Webinar)
มุมมอง 798ปีที่แล้ว
Benefits of Battery Testing - How To Perform Capacitance Test (Protec August 2022 Webinar)

ความคิดเห็น

  • @YuHsiangLin-d5z
    @YuHsiangLin-d5z 24 วันที่ผ่านมา

    Thanks for your great video! Does that mean when you measure H1-H2 ( 3 phase delta for example), the number of watts shows on the power factor test set is single phase iron core loss? Summation of each phase reading of watts equal to total iron core loss?

  • @KHS-t3i
    @KHS-t3i 25 วันที่ผ่านมา

    I'm a young man living in Korea. When I used the M4100 model today, I got this same error message. Switch 1 and 2 were the same as shown in the video, and I think I pressed it hard at the time. I want to do it again as you told me and make a normal measurement. Thank you.

  • @nohanageh996
    @nohanageh996 27 วันที่ผ่านมา

    Thank you for this video It is very important to me, but during my battery test, the injected current was 9 A and the receiver reads 3.5, is there a mistake?

  • @isaactuffuorbiney571
    @isaactuffuorbiney571 3 หลายเดือนก่อน

    Why did you provide a jumper in the voltage measurement across the resistances too? Couldnt we have connected the other end too across C2?

  • @erickirk6542
    @erickirk6542 3 หลายเดือนก่อน

    Awesome

  • @onesmushangula3116
    @onesmushangula3116 4 หลายเดือนก่อน

    Thank you so much!

  • @emedina47
    @emedina47 4 หลายเดือนก่อน

    Magically appears lol, this doesn't even go into changing the adapter settings on your PC

    • @DingleBerry817
      @DingleBerry817 13 วันที่ผ่านมา

      it's not always necessary to change the port settings on the PC

  • @muhammadshabbir8224
    @muhammadshabbir8224 4 หลายเดือนก่อน

    No more production of PFL22M1500J . Dis continued items

  • @ProtecEquipmentResources
    @ProtecEquipmentResources 5 หลายเดือนก่อน

    For Rental requests for the GE TVRMS2, go here: protecequip.com/products/general-electric-tvrms2-secondary-injection-test-set

  • @greatibekwe1779
    @greatibekwe1779 5 หลายเดือนก่อน

    Thanks for the insight. Can this be done with only an AC voltage and a voltmeter

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 5 หลายเดือนก่อน

      You might be able to do this with only an AC voltage source and (2) precision voltmeters. One for the voltage source on the primary and one for the secondary voltage. This might work great for a single-phase transformer. However, when you get into a 3-phase transformer testing, your meters and your source are going to have to become a bit more complex. You will now have to monitor both phase-to-phase and phase-to-neutral voltages and their phase relationships to one another. This is dealt with by having the test equipment (TTR) apply the appropriate vector math for the configuration of the transformer being tested. You will find that most of these pieces of test equipment will calculate accuracies or % error based on having entered in nameplate information. Probably the most significant response to this question is that commercially available test equipment will by necessity have certain safety and convenience features built into them. Automatic Discharge Single Equipment Grounding Point Demagnetizing Feature Easy Access to transformer configuration selections and connection Diagrams Pass/Fail indications based on imbedded industry standards and programed nameplate data. Finally, with a piece of test equipment designed for performing TTR tests, you can have an electronically generated report available for your customer within minutes.

  • @nihatdiler6709
    @nihatdiler6709 5 หลายเดือนก่อน

    A detailed and carefully prepared training video. Congratulations.

  • @wyewound
    @wyewound 6 หลายเดือนก่อน

    Thanks

  • @sango8511101
    @sango8511101 6 หลายเดือนก่อน

    is there any difference between demeganize high voltage side or low voltage side? just know that if demegnize from voltage side needs more currents

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 5 หลายเดือนก่อน

      From Bret Hammonds: The best approach to demagnetizing a transformer has been being debated for as long as I can remember. The answer might actually be based on who you ask. If I understand your comments correctly, it is as you stated. Demagnetizing from the secondary side of the transformer will require a greater amount of current than it would from the primary, even though it can be performed from either side of the transformer. However, I took it upon myself to contact a test equipment manufacturer concerning this question. Their recommendation was to demagnetize from the primary of the transformer. They also recommended that you demagnetize the transformer on each of the phases, and not just one. The best recommendation that I might give is to contact the specific equipment manufacturer and get their input regarding this matter.

  • @youssofasiry7233
    @youssofasiry7233 6 หลายเดือนก่อน

    Thanks for clear explanation and all details. I have question regarding this subject can I depend on excitation current result during TTR test ? If we have result zero current in one phase What is the possible reason? Also we did the winding resistance test and all phase give us reading within the limit. Transformer Dyn11

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 6 หลายเดือนก่อน

      Bret Hammonds from Protec answering: Excitation tests with a TTR are valid if you can establish a pattern such as a High-Low-High relationship of excitation values between phases. You may not be as successful at trending specific excitation values if you are not using the same instrument to perform your testing each time. The reason being that the specific excitation values are voltage dependent and will not trend if you use a TTR to do the testing at perhaps 8 to 120 volts on one occasion and a 10 kV power factor test set on another occasion. Regarding your question about an excitation current value of zero (0) on one phase of a three-phase transformer, the fact that you were able to perform winding resistance testing with good results confirms that you were able to saturate the core of the transformer and were not struggling with a tap connection or open winding issue. It’s difficult to say exactly why you may have gotten a zero-excitation test result on one of the phases. It may be that a low voltage instrument such as a TTR was, in this case, simply not adequate to properly perform excitation tests on this transformer. This would of course be only one possible explanation and may require further investigation to establish the actual cause of this test result.

  • @MarkSeager-dp2kg
    @MarkSeager-dp2kg 6 หลายเดือนก่อน

    Can TDR be effective for underground non shielded power cables? For example, could a TDR measurement be performed on a PV source circuit, containing 2 500kcmil conductors run underground in conduit?

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 6 หลายเดือนก่อน

      Hi Mark, thanks for your question. From Bret Hammonds: The technology behind TDRs is ideally suited for two conductors separated by a homogeneous (equivalent) insulation such as what you would find in either a shielded cable or one with a concentric neutral. The case that you have presented is less than ideal for use of a TDR since it is only able to detect very significant changes in impedance such as an open circuit or a short circuit. Having said that, it might be possible under some very unique circumstances for a TDR to be helpful in finding a fault in such a situation as what you have described. Those circumstances would include: - Using either a grounded conductive conduit for your return or the two separate cables that are running through the conduit. In either case you would NOT have a homogeneous (equivalent) impedance throughout the distance of the cable run. AND - A significant fault that is either completely open circuited ( ~ ∞ ohms) or a very low impedance (for all practical purposes considered to be a short circuit between the conductors.) If the fault is a high impedance fault, which is often the case, then the TDR will NOT be able to see the fault without being integrated into a more elaborately featured cable fault locating system.

  • @themalpowerplant.wonderful
    @themalpowerplant.wonderful 7 หลายเดือนก่อน

    Hello Sir, I have DC system with a lot of batteries but each battery has 6 pole, 3 + and 3 -. How to measure? Thankyou Sir

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 6 หลายเดือนก่อน

      The attached “Battery Testing Guide” from Megger does a good job of addressing this question. The explanation is on page 15 and references Figure 1(page 6): protecequip.com/media/7183/meggerbatterytestingguide.pdf

  • @markseager8386
    @markseager8386 8 หลายเดือนก่อน

    Great video. I’ve conducted hundreds of insulation resistance tests on power cables installed during new construction and can tell you guys know your stuff

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      Thank you for the generous praise! Glad to have you and your experience on commissioning!

  • @Moviesfans2157
    @Moviesfans2157 8 หลายเดือนก่อน

    What to do if tan delta value is above Acceptance value in motor.Need to do any maintenance

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      Thanks for your question. If the values associated with this type of testing are questionable, perhaps it would merit further investigation such as reviewing previous test results to establish a trend, performing a tip-up tests as an indication of voltage dependency for partial discharge. It may even be helpful to perform PD testing prior to moving into more impactful maintenance measures.

  • @aregawishishay
    @aregawishishay 8 หลายเดือนก่อน

    thanks for the detail explanation. one question why the winding resistance result is increasing to both direction from the main tap(nominal)

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      Thanks for your question. A transformer that has a resistive LTC on the secondary will display this kind of characteristic that increases as you move away from the nominal position in either the raise or lower direction. In either of the extreme positions (16R or 16L), all of the regulating winding will be included in the circuit and represent the highest winding resistance values. Each step away from the neutral position will represent a slightly larger amount of winding slightly increasing the winding resistance. In the case of a 16 raise and 16 lower tap switches with a neutral position in the middle, the difference between the raise and lower tap positions is a reversing switch. While that polarity of the winding included in the circuit may be opposite for the raise and lower taps, the amount of winding resistance would be comparable to the corresponding position in the opposing polarity.

  • @protossid
    @protossid 8 หลายเดือนก่อน

    Thank you Sir, very informative video

  • @14IEA
    @14IEA 8 หลายเดือนก่อน

    This is a great video! However, was not clear for me how can be possible to have shorted turns even if it passed ratio test? Thank you!

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      Thank you for the comment and question. The greater the number of turns in a winding the less of an impact one or two shorted turns may have on the ratio of the transformer and may not be significant enough to cause it to fail the (+/- 0.5%) industry standard for pass and fail criteria. However, it may cause enough of a change in comparison to previous excitation current tests or comparison to excitation tests of other phases to merit further investigation. This is why, in many cases if we perform one of these tests, we’ll perform both. It would be great if we had one test or one piece of equipment that would give us a full picture of the health of a transformer, but it just isn’t so. It sometimes takes 2 or 3 pieces of the puzzle to give us a clear representation of what’s going on with a transformer and its health. The number of shorted turns may not be significant enough to fail the ratio test, but other tests such as the excitation tests and winding resistance tests will produce results that perhaps cause enough concern to merit further investigation as to why test results aren’t more comparatively acceptable. Hope this helps!

  • @jluke6861
    @jluke6861 9 หลายเดือนก่อน

    Thank you for the Great Video.

  • @zmjpower
    @zmjpower 9 หลายเดือนก่อน

    Thank you for sharing

  • @SHAHZADAHMAD.ELECTRICAL
    @SHAHZADAHMAD.ELECTRICAL 9 หลายเดือนก่อน

    hello, please need price this tester

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 9 หลายเดือนก่อน

      Hi, you should contact Megger sales within your country to get a quote for purchase. megger.com/. If you are within the US and looking for a rental, you can contact us at (866) 352-5550 to get a rental quote. Thanks!

  • @ProtecEquipmentResources
    @ProtecEquipmentResources 10 หลายเดือนก่อน

    Watch our next Transformer Series video on Transformer Excitation Current here: th-cam.com/video/fheIzfl7K-Y/w-d-xo.htmlsi=x5WpDXJCb4Xn4maR

  • @mortezakarimi7538
    @mortezakarimi7538 10 หลายเดือนก่อน

    The video was decent. I wonder how this device reduces voltage drop error on the primary winding

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      I’m not completely sure of the context of this question, but I am suspecting that it may have been related to the difference in how measurements may at one time have been made as opposed to the way they are currently made from a concern for safety. If we were to apply a voltage to the secondary and measure the voltage across the primary of a transformer, the potential at the primary could be lethal and perhaps more difficult to meter. However, if we were to apply a voltage to the primary and compare it to the secondary, then the voltage is much lower and less difficult to meter on the output of the instrument, perhaps making it more accurate and safer than if we applied a voltage to the secondary.

  • @ewenclooney3979
    @ewenclooney3979 11 หลายเดือนก่อน

    Solid knowledge sharing… exactly what I want to know. Keep this up!

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 11 หลายเดือนก่อน

      Glad you like it! We will be doing another webinar on Transformer Winding Resistance this Thursday and will be adding it to the TH-cam library next week!

  • @Porny821
    @Porny821 11 หลายเดือนก่อน

    I'm using this setup for a string of 92 cells. Some of the BVMs read 0v, but only some times. Is it just finicky hardware?

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 11 หลายเดือนก่อน

      Maybe...if you are going to use more than 60 cells, you have to connect back from the last BVM to the power and signal module. Additionally, you need to make sure the first BVM goes on the NEGATIVE terminal of the string. Finally, if the BVMs continually read up to a particular BVM, check the input and output ports of that BVM.

  • @ProtecEquipmentResources
    @ProtecEquipmentResources 11 หลายเดือนก่อน

    Watch our video on Partial Discharge (PD) Testing: Exploring Online Techniques, here: th-cam.com/video/8uOuIaJctno/w-d-xo.html

  • @krishnasimhavemulapalli7124
    @krishnasimhavemulapalli7124 ปีที่แล้ว

    This video is absolute 💎

  • @raminmollahajloo4059
    @raminmollahajloo4059 ปีที่แล้ว

    Thank you 🙏🏼 for your information

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    Watch Tom's 5-Hour Ultimate Cable Fault Locating Webinar here: th-cam.com/video/Z0_nnk7jQW0/w-d-xo.htmlsi=PLXGkn9Q8DXAshqJ

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    To learn more about Insulation Testing, watch our Maintenance Series video "Understanding Insulation Resistance Testing" here: th-cam.com/video/8nwUzTyrFS0/w-d-xo.htmlsi=rh6spjiReQwcUpUt

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    To learn more about hipot testing, watch our other Maintenance Series Video "Understanding High Potential Testing" here: th-cam.com/video/gJ982SuNWwM/w-d-xo.html

  • @soe2152
    @soe2152 ปีที่แล้ว

    Thank you for sharing. learn a lot.

  • @juanmolinae
    @juanmolinae ปีที่แล้ว

    hi, the humidity is necessary check before the test? in that case what std IEC apply

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 7 หลายเดือนก่อน

      It is possible that I missed Tom’s reference in his presentation to humidity in relation to one of the standards. It may be that this material is present in the standards, but not mentioned in Tom’s presentation. The standards that he referenced were: IEEE Std. 400.2-2013 IEEE Guide for Field Testing of Shielded Power Cable Systems Using Very Low Frequency (VLF) (less than 1 Hz) IEEE Std. 400.3-2006 IEEE Guide for Partial Discharge Testing of Shielded Power Cable Systems in a Field Environment IEEE Std. 400.4-2015 IEEE Guide for Field Testing of Shielded Power Cable Systems Rated 5 kV and Above with Damped Alternating Current (DAC) Voltage IEC 60060-3 (2006) High-voltage test techniques-Part 3: Definitions and requirements for on-site testing IEC 60885-3 (2015) Electrical test methods for electric cables - Part 3: Test methods for partial discharge measurements on lengths of extruded power cables IEC 60270-3 (2000) High-voltage test techniques - Partial discharge measurements

  • @kizz24
    @kizz24 ปีที่แล้ว

    Can you do a video on how to calculate TTR without equipment?

    • @ProtecEquipmentResources
      @ProtecEquipmentResources ปีที่แล้ว

      Absolutely we can do a video on turns ratio testing and calculations covering a range of techniques and calculations. In the video we can discuss: Standards and Definitions Winding and Polarity Transformer Vector Group Codes ANSI Transformer Winding Phase Relationship IEEE C57.12.90 Measurement Method Nameplate Voltage / Nameplate Ratio / Voltage Ratio / Turns Ratio / Measured Voltage Ratio Recalculation Factor Testing Three-Phase Transformers with a Single-Phase Test Set Interpreting Test Results Coming soon....

  • @ukown3839
    @ukown3839 ปีที่แล้ว

    Very informative! Where can I find more?? 😁

    • @ProtecEquipmentResources
      @ProtecEquipmentResources ปีที่แล้ว

      Thanks! You can try this video from Tom Sandri from our April 2022 webinar Transformer Testing: Sweep Frequency Response Analysis: th-cam.com/video/q60RiGOnnyg/w-d-xo.html

  • @klaymanklogg8459
    @klaymanklogg8459 ปีที่แล้ว

    I really liked the content of the video, Great breakdown and explanation without getting too muddy in theory and mathematical equations. It helped to make the information jello a little more solid.

  • @rmorlayhe
    @rmorlayhe ปีที่แล้ว

    Any temperature correction factors to apply?

    • @ProtecEquipmentResources
      @ProtecEquipmentResources ปีที่แล้ว

      Anytime resistance measures are involved, particularly if you intend to trend, temperature corrections would apply. Many people use resistance as a spot reading, and do not apply temperature correction. If data is to be trended it is always a good idea to apply temperature correction. NETA Table 100.14.1 provides insulation resistance conversion factors (20 degree C).

  • @muhammadshabbir8224
    @muhammadshabbir8224 ปีที่แล้ว

    PFL22M1500J now production is closed.

    • @ProtecEquipmentResources
      @ProtecEquipmentResources ปีที่แล้ว

      Correct, it is now replaced by the SG32-1500. You can find more about the SG32 here: protecequip.com/products/megger-sg32-1500m-power-cable-fault-locator.

  • @mattdelaney584
    @mattdelaney584 ปีที่แล้ว

    Have you had any issues with using the MEGGER BVM modules? Recently had issues with the modules dropping communication to the test set and not collecting data sporadically throughout a discharge test.

    • @ProtecEquipmentResources
      @ProtecEquipmentResources ปีที่แล้ว

      Yes! Typically happens when discharge rates are 30 minutes and faster. What's happening is the current flow at these rapid discharges are causing large magnetic fields, which is interfering with the unshielded cables used on the BVMs. The only solution is use another product like the Alber. Look at the BCT-2000, I think this is the one I have used. alpinepowersystems.com/manufacturers/alber/. The update rate is much faster than the BVM as well. We don't carry this Alber unit but not hard to find. For fastest charges with high current, short duration, this is a very common problem with the Megger. I feel your pain, been there. - Tom

    • @mattdelaney584
      @mattdelaney584 ปีที่แล้ว

      @@ProtecEquipmentResources Thanks Tom. ya we were thinking the same but also thought we were having PowerDB issues with the automated form we were using. Is there a effort to change the cables to shieled? or is Alber coming out with a updated version of the BCT-2000. I have used the BCT but it wasn't easy to come by. Does Protech plan to add BCTs in there fleet soon?

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    This is an old, shaky video, but good stuff! If you have any questions for Tom, please ask below!

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    This is an old, shaky video, but great content. If you have any questions for Tom, please ask below!

    • @themalpowerplant.wonderful
      @themalpowerplant.wonderful 7 หลายเดือนก่อน

      Hello Sir, I have DC system with a lot of batteries but each battery has 6 pole, 3 + and 3 -. How to measure? Thankyou Sir

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    Pro Tip: Make sure you are getting the Doble DTA Pro software! ⚡⚡Comment below if you have any questions for Bret.

  • @BSSandhu
    @BSSandhu ปีที่แล้ว

    Thanks...it works

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    Don't Fret, Call Bret! Feel free to ask Bret a question below.

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    Feel free to ask Tom Sandri and questions below!

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    This is an old Tom Sandri video but still very valuable Torkel info! Ask Tom any questions below and we will respond.

  • @ProtecEquipmentResources
    @ProtecEquipmentResources ปีที่แล้ว

    QUICK FIX: The newest paddles (hand interlock switches) are a 2-position switch. Only squeeze HALF-WAY (one click) to satisfy the interlock.

    • @getbetterben4312
      @getbetterben4312 4 หลายเดือนก่อน

      isn't it a 3 position switch? out, half-way and fully depressed. Out and Fully Depressed turn off the test set.

    • @ProtecEquipmentResources
      @ProtecEquipmentResources 4 หลายเดือนก่อน

      @@getbetterben4312 Correct. The safety switch is designed so that it will only allow the output of the test set to be energized if the switch is in the position between completely released and completely depressed. The reasoning is that if the operator were to contact something energized, their muscles would contract causing the operator to fully depress the safety switch. If something like this were to occur, then the desired response would be to de-energize the output of the test set upon fully depressing the switch. So to summarize, when released entirely, the test enable/safety switch is off. When squeezed to the first resistance click (half way), the test enable/safety switch is on. When squeezed to the second resistance click (fully depressed), the test enable/safety switch is off.